Waukee Community School District’s 10-year Facility and Financial Plan was created to help map our future growth and development. This page contains details about where the district is in the plan, including start and completion dates.

Brookview Elementary – Addition

  • Project is approximately 75% completed
  • Both additions are fully enclosed
  • Exterior brickwork is finishing up
  • Interior finishes are starting to be installed

Northwest High School – New Construction 

  • NWHS Entire Site Video – 3/16/2021
  • Project is approximately 90% completed
  • Exterior site work and landscaping is getting completed
  • Interior finishes are being installed throughout
  • Equipment and fixtures are being installed
  • Punchlist inspections are occurring and are scheduled for the next month

Sugar Creek Elementary – New Construction 

  • Project is approximately 40% completed
  • Exterior site work is resuming
  • Interior walls are being framed and drywalled
  • Electrical, mechanical, and plumbing system rough-ins are continuing

VMLC Preschool/Office – Addition

  • Project is approximately 50% completed
  • Drywall is being installed throughout
  • Windows and exterior wall coverings are being installed
  • Interior finishes are starting to be installed in some areas

Prairieview School – Addition

  • Project is substantially complete
  • Temporary Certificate of Occupancy was issued by the City of Waukee
  • Fitness equipment is scheduled to be installed in mid-April

Eason Elementary – Addition

  • Project is approximately 25% completed
  • Precast concrete roof has been installed
  • Underground utilities are installed
  • Interior floor and storm shelter roof are being prepped for concrete

Timberline Stadium Improvements – Phase #2

  • The contractor has been determined and a pre-construction meeting is scheduled
  • Groundwork on the soccer fields should begin in the next couple of weeks

Middle School #5 – New Construction 

  • In design with FRK Architects; Bids in May 2021

WCSD Aquatics Facility – New Construction 

  • In design with RDG Planning & Design; Bids in Nov 2021
  • Schematic designs are being developed based on input from stakeholders

Brookview Elementary – Addition

  • Project is approximately 50% completed
  • Both additions are fully enclosed
  • Exterior finishes are starting to be installed
  • Electrical, mechanical, and plumbing rough-ins are nearly completed

Northwest High School – New Construction 

  • NWHS Entire Site Video – 2/10/2021
  • Building is completely enclosed as of this week
  • Project is approximately 90% completed
  • Interior finishes and cabinetry are being installed throughout
  • Equipment and fixtures are being installed
  • Punchlist inspections are occurring and are scheduled for the next two months

Sugar Creek Elementary – New Construction 

  • Project is approximately 35% completed
  • 2/3rds of the building is essentially dried-in
  • Interior walls are being framed
  • Electrical, mechanical, and plumbing systems are being roughed-in

VMLC Preschool/Office – Addition

  • Project is approximately 35% completed
  • The additions are essentially dried-in
  • Interior walls are being framed
  • Electrical, mechanical, and plumbing systems are being roughed-in

Prairieview School – Addition

  • Project is approximately 99% completed
  • Temporary Certificate of Occupancy was issued by the City of Waukee
  • Final punchlist items are being addressed
  • Landscaping will completed once the weather allows
  • Fitness equipment is scheduled to be installed in late March

Eason Elementary – Addition

  • Project is approximately 5% completed
  • Masonry walls are being constructed
  • Underground plumbing and electrical is being installed

Timberline Stadium Improvements – Phase #2

  • Project is currently out for bidding.

Middle School #5 – New Construction 

  • In design with FRK Architects; Bids in May 2021

WCSD Natatorium – New Construction 

  • In design with RDG Planning & Design; Bids in Nov 2021
  • Stakeholder design meetings to occur over next two months

WMS Gym Cooling Project

  • Project completed

Timberline Stadium Improvements – Phase #1

  • Project completed

WHS-PVS Parking Lot Improvements

  • Project completed

Additional Ongoing Projects

  • WHS Tennis Court Resurfacing
  • WHS Fire Alarm Replacement
  • WHS Roof Replacement
  • Playground Soft-Surface Improvements Project
  • PVS-WHS Paving improvements Phase 3
  • Douglas Pkwy Extension Project